3. Operation

Initial start-up

It is essential to contact our Customer Service to ensure that your system is commissionned in complete safety and
to benefit from the manufacturer's guarantee.

Final start-up sequence

3
4
5
-
34008486EN/AC
Page 28
1
2
I
O
I
O
1 - Be sure that the manual bypass switch
(1) is in normal position, like shown on the
picture.
2 - Put the Normal AC source input switch
(2) in "1" (ON) position
3 - Set the upstream circuit breaker (not
included) to the "I" position (ON).
3
The equipments are powered via the
Bypass AC source, but not protected by
the UPS.
Batteries are recharging, an 8 hour
recharge period is necessary to get full
backup time.
LED (3) is ON, LEDs (4) and (5) are green.
4
5
3- Press the "I" button (1) more than 3s.
2
6
The buzzer beeps once, and after UPS
7
internal test sequence, the LED (2) is ON.
If internal test sequence fail, see chapter 7
LEDs (3), (4), (5) are green.
The equipments are protected by the
UPS.
If LED (6) or (7) is ON, an alarm has
occurred (see the "troubleshooting"
section).