Firewood Box Concrete Pad Construction:
Call 811 for information on underground utility marking. Select desired location and excavate 44"Lx 50"W x 10"D
area for concrete pad. Fill excavated area with approximately 6" of ¾" clean gravel, compacting every 3". Frame re-
maining 4" with 2"x4" lumber to create a level pad. (Be sure 2"x4" wood frame is perfectly level, front to back and side
to side) See attached drawing for details of steel reinforcement rod placement. Fill 2"x4" wood frame with a 4,000 PSI
strong concrete mix.
*Allow pad to cure for minimum of 48 hours.
4"
6"
Construcción concreta del cojín Para la caja de lena:
Seleccione la localización y excavan 44" Lx 50" W x 10" D para el cojín de concreto. Llene el área excavada
de aproximadamente 6" de ¾" grava limpia, compactando cada 3". Capítulo 4" restantes con madera de construcción
2" x 4" para crear un cojín nivel. (Sea sure el marco de madera 2" x 4" es perfectamente nivel, frente
hay atrás y lado a lado) vea el dibujo atado para los detalles de la colocación de acero de la barra del refuerzo.
Llene el marco de madera 2" x 4" de una mezcla de hormigón fuerte de 4,000 PSI.
*Permita que el cojín cure para el mínimo de 48 horas.