RADJUSTEMENT OF THE OTHER WET ROOMS
In accordance with the French « dwelling regulation » airflow rates are:
Bathrooms
Single toilet
Several toilet
Other humid rooms: laundry etc...
INSTALLATION OF YOUR DOUBLE FLOW AKOR
The installation and the connection have
do be done by qualified personnel
ELECTRICAL CONNECTION
The electrical connection must be carried out
in accordance with wiring diagram herewith
and in compliance with the regulations in force
in the country of installation :
Reminder :
You must provide a single pole protection
with an air gap of at least 3 mm.
Independent from the general panel, you
must provide a temporised 2A fuse (motor
accompaniment) for safety protection.
AKOR SYSTEM
The unit should be installed in an accessible position in an attic or similar space and adjacent to. We recommend the
insertion of glass wool or similar fibre between the fan box and the floor, in order to reduce noise transmission.
IMPORTANT ADVICES
Provide for an empty space of 450 mm on the top of the unit in order to dismantle easily the heat
exchanger during maintenance operation
Install the unit in a lightly slope in order to evacuate the condenses by the drain which is located on
the side of the unit.
Not forget to connect the drain with a Ø15 mm pipe connected to the spoilt water network (provide a
constant slope and insulated the pipe in order to avoid any freezing risk)
Dwelling T3 to T7
Wooden
plate
regulator set at 15 m3/h
30 m³/h
30 m³/h
15 m³/h
15 m³/h
fuse 2A
External insulation
Connector
Ø15
Condenses connection
regulator set at 30 m3/h
Available in option :
-
-
Insulated
panel
pre-heater battery
re-heater battery
G/Y
Blue
Brown
Black
G/Y
Blue
Brown
Black