H-4465, H-4466, H-4467
H-7959, H-7960, H-7961
FLEXIBLE DELINEATOR
POST WITH BASE
1. Clean and dry pavement surfaces prior to
installation. Surfaces should be blown clean at a
minimum of 90 psi.
NOTE: Minimum installation temperature for
pavement is 70°F and 40°F for air. If pavement
is less than 70°F, the surface must be warmed
with a torch or heat lance.
2. Remove clear liner from top of H-4467 Butyl Pad.
Place exposed side of butyl pad onto the pavement
and apply pressure.
3. Remove the white release liner to expose the upper
adhesive surface.
NOTE: If pavement is less than 70°F, the top
surface of the butyl pad must be lightly
warmed with a torch or heat lance for
approximately 2-5 seconds.
4. Immediately place the black plastic base in the
center of the butyl pad. Flow arrows should align with
the direction of traffic. Apply pressure. (See Figure 1)
Figure 1
PAGE 1 OF 3
1-800-295-5510
uline.com
INSTALLATION
5. Align the hole in the post with the middle hole in the
base and insert the post. (See Figure 2)
Figure 2
6. Using a hammer or rubber mallet, insert plastic pin
into the center hole to secure the post to the base.
(See Figure 3)
Figure 3
7. Allow up to two hours for butyl pad to fully adhere.
Para Español, vea página 2.
Pour le français, consulter la page 3.
0821 IH-4465