Installation Procedures
Select the following places to install indoor unit
(1) Location where the condensate water can be drained out smoothly
and the drainage pipe can lean appropriately.
(2) Location where there is no obstacle at air inlet or outlet. And the
places which will not alarm or not be in short circuit.
(3) Location around which the frosting temperature is below 28°c and
the relative humidity is below 80% (when the unit is installed at
place with high temperature, pay main attention to frosting issues,
for example the unit can be equipped with heat insulation).
Take it into account that if the place is strong enough to support the
unit. If not, please strengthen it with reinforced plate and horizontal
plate.
Suspension Installation
Suspend the bolt with 4 M10 or W3/8. Fasten the bolt to make every bolt bear the load of 50kg.
The suspension bolt should be about 95mm extending outward of ceiling.
When the ceiling exists already
1.Open a hole on the ceiling, and set the dimension appropriate for the installation.
2.Fasten the bolt (purchased locally) on the correct position.
3.After suspending indoor unit, install the template paper on the position of panel with 4 bolts,
then adjust the height according to the below procedure; (the length from ceiling to unit bottom is
40VU007~0182-7G-QEE: 63mm)
4. Check if the unit is horizontal with a gradient. If not,
the unit will leak water or float switch works badly.
5.Fix the unit after levelness adjustment.
7