5 Important installation instructions
5.5

Installation sequence

Carry out the following steps to commission the Conergy
SmartControl System:
1. Register the PV system on the system monitoring portal
2. Install the hardware components.
3. Connect the hardware components (including CAN
cabling)
4. Check the functions of each hardware component.
Until the system is registered on the system monitoring
portal, the Conergy SmartControl can transmit data, but it
cannot be assigned to the system and is lost! Conergy
recommends that you register the system before installation.
You can transfer the latest firmware to the components at any
time using the Conergy ControlCenter software.