I N S TA L L AT I O N

Part 2b: Wire the Fixture (Emergency Operation)

The commercial Clear Connect - Type X Ketra D3 and LVS LUT-SHUNT-A-TD, when installed together, form an approved
emergency lighting system in accordance with NEC
with NFPA101, is required to maintain this compliance.
1.
Run power to junction box
a.
Remove the junction box's outer cover by pressing down on the outer latch and pulling the cover toward you.
Note: A licensed electrician should perform all the wiring tasks. All electrical connections must be made within
the junction box.
b.
Run the conduit in (and out, if this is one downlight in a sequence).
Note: Maximum of ( 8 ) no. 12 AWG (4 mm2) through branch circuit conductors suitable for 165 ˚F (75 ˚C)
permitted in the box.
c.
Run the building's power line wires* into the junction box.
2.
Install the LUT-SHUNT-A-TD in accordance to LVS installation instructions wired to the circuit feeding the Ketra D3.
3.
Splice the wires
a.
Using the provided connectors, wire the D3's flying leads according to the diagram below.
Note: The Ketra D3's hot (black) will connect to the RED #4 on the LUT-SHUNT-A-TD according to the diagram below.
Note: The Ketra D3's neutral (white) will connnect to the emergency neutral and White/Blue #2 on the
LUT-SHUNT-A-TD according to the diagram below.
Regular Utility
Power
ULR 1008 Transfer
Switch or Equal
Emergency
Power Source
20 A Circuit
Regular Utility
Normal/Emergency
Power
Circuit Panel
b.
Make sure the housing is installed and grounded in accordance with all national and local codes.
c.
Replace the junction box's outer cover.
4.
Test the wiring
a.
Apply power to the D3. The emitter should immediately come on to 3000 K (warm white).
Note: If the emitter comes on red, see Diagnostic Colors, page 19.
b.
Wait several minutes while the D3 tests its installation conditions. Then use the color to determine whether
installation was successful:
If the light stays at 3000 K, installation was successful.
If the light changes color, a problem has been detected.
Note: Magenta can indicate success or failure. It indicates success if there are no other powered-on Ketra
devices within 50 ft (15.2 m); otherwise, it indicates a problem.
To troubleshoot problems, see Diagnostic Colors, page 19.
c.
Emergency Lighting Testing: Press and hold the test button on the LUT-SHUNT-A-TD. The D3 should turn off for
approximately 2.5 seconds then come back on at full brightness.
d.
After verifying a successful installation, remove power and continue to Part 3.
12 | D3 INSTALLATION GUIDE
Article 700 and NFPA101. Monthly and annual testing, in accordance
®
Normal/Emergency
Neutral
20 A Circuit
Power
Normal/Emergency
Line/Hot
Circuit Panel
5 Black
6 White
Normal Voltage Sense
LVS Controls Emergency Device
for use with Ketra Loads
Normal Hot
Normal Neutral
Neutral
3 Red
1 Blue
2 White/Blue
UTILITY
POWER
4 Red
TEST
Normal/Emergency
Ketra D3
LUT-SHUNT-A-TD
© 2019-2022 Ketra, Inc. All rights reserved.
P/N 3662708 Rev A

Publicidad

Tabla de contenido

Solución de problemas

loading

Tabla de contenido