A - ENGLISH
MACHINE SET UP & INSTALLATION
UNCRATING MACHINE
Be sure and check packing carton for any damage. Immediately report any damage to carrier.
Check contents of package to ensure that the following items are included:
1.
Machine
2.
Batteries(x2)
3.
Squeegee assembly
4.
Owner's Manual
5.
Electric Battery Charger Manual (if equipped)
6.
Connecting wire for battery and charger (if equipped)
7.
Brush
BATTERY DISASSMBLY AND INSTALLATION
1.
Switch off the main switch. (47)
2.
Remove the recovery tank. (2)
3.
Remove the bolt from batteries. (16) Remove or change batteries.
4.
Install the batteries on the machine according to the diagram below.
5.
Install the recovery tank.
WARNING !
Do not connect+ to +,or - to-,when disassembly or install the batteries. It is very dangerous.
BATTERY CHARGING
Charge the batteries. (see Maintenance section)
MACHINE SET UP
Pre-operation checks
1.
Sweep or dust mop the surface to be cleaned.
2.
Check that squeegee is properly installed.
3.
Lower the squeegee (33) with the lever. (26)
4.
Ensure batteries are fully charged. (see Battery Charging section)
5.
Check that brush is properly installed.
A - 4
INSTRUCTIONS FOR USE
MA50 15B - 56091128
7/2014