Descargar Imprimir esta página

Pool Technologie UNO Instrucciones De Uso página 20

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 30
5. INSTALLING THE UV REACTOR
It is imperative that you read all the instructions in this manual before
For ease of maintenance, we recommend using a bypass.
-
The reactor must be installed in a vertical position (water inlet at the bottom)
-
Reactor
The reactor must always be located after the filter and before any other auxiliary appliance (heating).
-
A clear space of at least 1,000 mm must be provided for above the reactor for a JUSTSALT UV 25, or 700
-
mm for a JUSTSALT UV 15, for maintenance of the lamp and quartz.
The direction of flow from low to high must be respected.
-
The maximum network pressure must never exceed that of the reactor (3 bar).
-
If there is a risk of overpressure, it is recommended that an automatic bleed or relief valve be installed
to keep the line pressure below that of the reactor.
If a bypass is used for heating, the UV unit must be installed before the bypass.
-
The reactor is designed to be placed on the ground.
-
Please put on protective gloves before starting the installation.
700/1,000 mm
operating the reactor.
Downstream
valve
Bypass valve
Upstream
valve
6

Publicidad

loading