Operating Instructions; Calibration And Set-Up Of The Components; Routine Maintenance; General Cleaning Of The Station - CTX PANEL CLASS PH 5-7 - RX Manual De Instalación, Uso Y Mantenimiento

Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

OPERATING INSTRUCTIONS

Calibration and set-up of the components

For CONTROL PANEL PH-RX installation operations, refer to these operating instructions.
For wiring, calibration and pump operation setting of tool pump functions, refer to the pumps' manual
included in the package.
For all other installation and adjustment procedures of the probes/electrodes, refer to their use and maintenance
manuals.

ROUTINE MAINTENANCE

Periodic maintenance must be carried out in order to obtain maximum performance of the control station. We
also recommend that you follow our maintenance programs and join a scheduled service with one of our
Authorised Service Centres.
The following is a general table indicating the maximum time of maintenance intervals.
Control station maintenance intervals are defined by the conditions in which it operates. More precisely, the
information in the maintenance table is indicative since it refers to a theoretical system. In fact, each system
according to the way it is structured has its own maintenance requirements. Therefore, the maintenance
technician must evaluate the interval of time for any replacement of parts.
Before carrying out any of the maintenance operations listed below, electrically disconnect the control
station from the line's switch where it is located.
Before carrying out any of the maintenance operations listed below, stop the flow of water that reaches
the station from the system and depressurise it by completely opening the sampling valve.

General cleaning of the station

Periodically clean all surfaces of the station. Only use a damp cloth without adding any solvent or product.

Cleaning the water filters

Wait until no water comes out from the hydraulic system. Loosen the filter unit tray and remove the filter cartridge
placed inside, being careful not to lose the relative seals. Place the cartridge under running water and, using a
soft brush, remove all impurities from the filter. Reassemble the filter cartridge and the filter tray on the system,
being careful to reposition the seals correctly. Completely close the sampling valve and restore the water flow in
the circuit, gradually opening the valves and by bleeding air from the system. Connect the control station again
and check the operating conditions after it carries out the initial test.
General cleaning of the station
Water net filter cleaning
Probe cleaning
Hydraulic system inspection
Tab. 1 – Recommended maintenance intervals
TIME INTERVALS
1 month 2 months 3 months 6 months
X
X
X
X
ENGLISH 53

Publicidad

Tabla de contenido
loading

Productos relacionados para CTX PANEL CLASS PH 5-7 - RX

Este manual también es adecuado para:

Qpa5s11001ct

Tabla de contenido