Hubbell System-One pd2104 Instrucciones De Instalación página 4

Boquilla horada-piso system-one con barrera de fuego
Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

10. Use the provided floor gasket or apply a ¼ [6.3mm] thick
continuous bead of electrical type of RTV silicon sealant
compound fully around the perimeter on the underside
of the flange (k), Fig. 2
11. Discard installation plate (j) and black spacer (o). Attach
Cover Assembly (k) to the service fitting using retained
screws. If purchased separately the cover assembly will be
supplied with additional mounting screws.
12. FOR NEW TILE FLOORS: Pour concrete, core hole and
Install tiles. Installer must make top surface of tiles and
flange flush. Seal entire periphery of the flange with grout.
ABANDONMENT PLATE INSTALLATION INSTRUCTIONS
(Purchased separately):
S1R6ADMTxx abandonment plates provide an approved
method of abandoning the Hubbell S1P6PTxx series fire
rated poke through. This product will maintain the fire rating
of the poke through installation.
1. Disconnect power and/or telephone/data of the poke through.
2. Remove cover assembly by removing screws (ax)
attaching cover to the can. See Figure 11.
3. Install black spacer (o) and abandonment plate item (ag).
Coat supplied screws with sealant compound to ensure
water tightness before installing. Coat cover perimeter to
ensure water tightness.
PRE-POUR TUBE (PPT) INSTRUCTIONS (Purchased separately):
Slide (3) tube segments (aa) together using dovetail joints.
Segments are identical except for location of holes (ab).
Assemble brackets (ad) as required as shown in figures 4 and 5.
Brackets are marked to assist assembly. Turn hexagonal head
screws (ae) horizontally to support the disc (at). Insert discs (at)
at top, center and bottom. Bend brackets (af) for center and
bottom positions to fit inside the assembled tube segments.
STEEL DECK INSTALLATION
1. Cut hole 8.06" to 8.12" in diameter into deck.
2. Install assembly into cut hole, see Fig.4. Check that the
assembly is installed plumb to the deck. Attach to deck
with sheet metal screws (not supplied).
3. Adjust the height of the assembly so that the top of the
cap protrudes above the maximum thickness of the
desired concrete pour.
4. Seal perimeter of PPT with tape.
PLYWOOD DECK INSTALLATION
1. Attach assembly to the deck with appropriate fasteners
(not provided). See Fig. 5.
2. Seal deck area around PPT with tape.
AFTER ASSEMBLY – Pour concrete and let cure. AFTER
CURE - Remove discs (at) and hexagonal head screws (ae).
Drive one of the segments (aa) downward until released
from the concrete. Brackets (ad) will remain inside the
resulting hole.
PD2463
(Page 2)
10/13
Fig. 4
Fig. 5
Fig. 6
PRINTED IN U.S.A.
(at)
(at)
(ab)
(ae)
(ad)
Fig. 7
(af )
(aa)
Fig. 8
Fig. 9

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

System-one pd2463

Tabla de contenido