STEP 1.
Find the drilling location at the rear of the cabinet, near
the top. See Figure A.
STEP 2.
Drill a ½" hole.
STEP 3.
Straighten the capillary tube. See Figure B. DO NOT KINK
THE CAPILLARY TUBE OR THE SENSING BULB.
STEP 4.
From top of heater, install sensing bulb down and under the
gas control valve so that the capillary tube is between the back
of the heater and the wall. Slide white cable clamp (provided)
onto sensing bulb and secure to the bottom of the gas valve
using the 10-24 x 3/8" screw provided.
STEP 5.
Secure P/N 1016899 CDV switch bracket to the BBSK control
switch (see Figure B) using two (2) #6 x 1/4" screws provided.
Secure the control switch and bracket to the right side of
the inner wrapper using prepunched holes and two #8 x 1/2"
screws provided. See Figure C. Note: Switch and bracket
must be installed to be outside the wrapper.
STEP 6.
Run the two control wires from the switch down the right
outside of wrapper. Connect one wire to the "TH" terminal
and one to the "TH-TP" terminal on the gas valve. See
Figure D. Slide a white cable clamp (provided) over both
wires and secure to wrapper using screw that secures the
floor shield.
STEP 7.
If heater is not installed to wall, follow instructions to do so.
STEP 8.
Remove and discard the lighting instructions supplied with
heater. Replace with lighting instruction supplied in BBSK kit.
STEP 9.
Place cabinet onto heater, the control rod should extend up
through the ½" hole in top of cabinet.
STEP 10.
Place the control knob onto the control rod and secure
by pushing down.
STEP 11.
Follow the lighting instructions to place the heater in
operation.
FIG. C
Right Side of
Inner Wrapper
5/8"
3"
2"
English Manual
BBSK INSTALLATION INSTRUCTIONS - ( OPTIONAL )
This kit must be installed by a qualified
installer or service technician only.
CDV15
CDV25/33
Right Side of
1-7/8"
Inner Wrapper
3-1/8"
FIG. A
CDV15
CDV25/33
FIG. B
FIG. D
2"
Page 10
13/16"
Control Unit
CDV Switch Bracket
TH
TH-TP
3-1/4"
6-1/2
3-1/4"
Capillary Tube
Sensing
Bulb
84517-C