11.) After installing the conversion kit, verify the location of the
Thermocouple and Igniter Pin using the illustration below.
12.) Note to installation technicians. Verify the manifold pressure by using a
3/8" flared T-junction at the location marked by the arrow below. Then using
a digital manometer verify that the pressure before the orifice is 7" W.C. Also
verify that the orifice spud has the
that the input rating of the appliance is correct.
Installing at Altitude
For installations at elevations above 2000 ft. contact your local dealer or gas
supplier before installing as input rating should be reduced approximately 4%
for each 1000 ft. above sea level. Refer to the National Fuel Gas Code.
Contact the Real Flame for more information at 1-800-654-1704
NATURAL GAS CONVERSION
Thermocouple
NOTE: Pilot housing removed for example only.
.25" .25"
.25"
#25
marked. This will allow you to verify
7
Igniter Pin
To Manometer