CABLE INSTALLATION
1) Feed incoming cable(s) through the grommet opening.
2) Remove required outer cable jacket leaving jacket at the closest lance point.
3) Secure the cable to the lance point with Velcro or nylon tie wraps as appropriate.
4) Using the cable management saddles, route the breakout fiber legs to the patching or termination point as shown in the
configuration drawings below:
ROUTING FOR BULK CABLE – FIELD TERMINATION
ROUTING FOR PRE-TERMINATED CABLING
DI-000-5WMNT-20A
Page 8 of 30