Fireplace Concrete Pad Construction:
Call 811 for information on underground utility marking. Select desired location and ex-
cavate 88" L x 60" W x 12" D area for concrete pad. Install four 8" diameter concrete
tubes to frost-line as per local code. Fill excavated area with approximately 6" of ¾" clean
gravel, compacting every 3". (Do not fill concrete tubes with gravel). Frame remaining 4"
with 2" x 4" lumber to create a level pad. (Be sure 2" x 4" wood frame is perfectly level,
front to back and side to side) See attached drawing for details of steel reinforcement rod
placement. Fill concrete tubes and 2" x 4" wood frame with a 4,000 psi strong concrete
mix.
* Allow concrete pad to cure for 48 hours.
Construccion Concreta del Cojín de la Chimenea:
Llame al 811 para obtener informacion sobre la utilidad de metro marcado. Seleccione la
ubicaci n deseada y excavar 88" de largo x 60" W x 12" D área de plataforma de concreto.
Instale cuatro 8" de diámetro de los tubos de hormigon a las heladas-line como por el
codigo local. Llene la zona excavada con aproximadamente 6" de ¾" limpia grava, com-
pactando cada 3". (No llene los tubos de concreto con grava). Marco restantes 4"con 2" x
4"de madera para crear una plataforma de nivel. (Asegúrese de 2"x 4" marco de madera
está perfectamente horizontal, de adelante hacia atrás y de lado a lado) Véanse los detalles
del dibujo para la colocacion de varillas de acero de refuerzo. Relleno de concreto y tubos
de 2"x 4" marco de madera con una mezcla de concreto 4000 PSI fuerte.
* Deje que la almohadilla para curar por un mínimo de 48 horas.