Cooper Lighting Streetworks Archeon Large Instrucciones De Instalación página 3

Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

Wiring (Figure 5.)
1.
Pull service wires through mounting arm and into
housing approximately 5" .
a. Three-terminal block (2-wire service): Connect line
service lead to terminal that is connected to black
factory-installed wire. Connect neutral service wire to
terminal that is connected to white factory-installed
wire.
b. Three-terminal block (3-wire service, 2 lines, 1
ground): Connect 1 line service lead to terminal that
is connected to black factory-installed wire. Connect
other line service lead to terminal that is connected
to white factory-installed wire. Connect ground
service lead to terminal that is connected to green
factory-installed wire.
c. Three-terminal block (3-wire service, 1 line, 1 neutral,
1 ground): Connect line service lead to terminal that
is connected to black factory-installed wire. Connect
neutral service wire to terminal that is connected to
white factory-installed wire. Connect ground service
wire to terminal that is connected to green factory-
installed wire.
d. No terminal block (3-wire service, 2 lines, 1 ground):
Connect 1 line service lead to black factory-installed
wire. Connect other line service lead to white
factory-installed wire. Connect ground service lead to
green factory-installed wire.
e. No terminal block (3-wire service, 1 line, 1 neutral, 1
ground): Connect line service lead to black factory-
installed wire. Connect neutral service lead to white
factory-installed wire. Connect ground service lead to
green factory-installed wire.
N
ote:
Terminals are numbered at the wire entrance of the
terminal block.
2.
If removed, return access door to hinge and swing the
access door into closed position and secure latch by
rotating 1/4 turn.
Arm Installation (Optional)
Mast Arm: Square Pole (Figure 6.) and Round Pole
(Figure 7.)
1.
Insert nut plate into pole and align insert holes with the
mounting holes in the pole.
2.
Insert threaded rods through the top and bottom holes.
Screw into nut plate.
3.
For round poles only - Install round plate adapter with
round side facing pole (Figure 7 .). Align holes top and
bottom.
4.
Insert the mast arm onto the threaded rods thru the top
and bottom holes.
5.
Install washers, nuts and Torque nuts using 1/2" open
wrench to 35~40 ft-lbs.
Installation Instructions - Archeon Large
Install Direction
Figure 4.
Three or
Four Position
Terminal Block
Figure 5.
Cover Plate
Arm
Figure 6.
COOPER LIGHTING SOLUTIONS
Hot Lead
Ground Lead
Neutral Lead
Threaded Rods
Nuts
Washer
Electrical Wires
Square Pole
IB521010EN
Installation instructions
Backup
Plate
3

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

Streetworks archeon medium

Tabla de contenido