2.- INSTALLATION INSTRUCTIONS
1.- Chose the right place to install the heater. It is necessary that a minimum clearance of 50 cm is allowed to ensure the best heating results.
Always maintain a minimum clearance of 50 cm from the heater to any combustible materials such as furniture and curtains.
2.- Open the carton at the indicated side and fix the feet without removing the heater casing (fig 1). The screws are in the accessories bag. Turn
the carton upside down to allow the heater to stand on its feet and remove the carton. Check that it is the correct model and that it is in good
condition.
fig 1
fig 2
3.- Take off the front panel by removing the two screws at the bottom of the heater.
4.- Set the heater in the selected installation area and mark the fixing points on the wall using a pencil. Use the heater fixing holes as a template
and mark the wall through the fixing holes. Drill the required holes into the wall.
5.- Fix the heater to the wall. Please note the weight of the heater is taken by the feet, the wall fixing screws are only to prevent the heater
overturning. If there is any doubt as to the strength of the wall please consult an expert. Storage heaters are very heavy and the installer
must ensure that they are securely fixed and that there is no possibility of them overturning.
6.- Connect the heater using the enclosed wiring diagram. Ensure that all connections are firm. Use silicone covered wire. Do not leave any
remaining wire inside the heater.
7.- Remove the inner front panel with the attached convector element.
Warning!
At the other side of this front panel there is a breakable thermal insulation panel. Both sides must be handle with care. Avoid touching the
insulation and the convector element.
8.- Do not disconnect the electrical elements. Remove the packaging then lift and recline the elements.
9.- Place the storage bricks carefully, with the flat side facing the back of the heater. Arrange two rows of bricks (fig 3). Should big bricks (ref
11072) are required they must be placed at the right side.
fig 3