Descargar Imprimir esta página

Volvo Penta 21330289 Instrucciones De Montaje página 6

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 9
This kit contains:
Designation
7" Display
Harness
Plastic frame (top installation)
Protective cover
Insert
Installation instructions
Installation, Volvo Penta 7" Display
IMPORTANT! Read through the complete instruc
tions carefully and install the Volvo Penta 7" Dis-
play (color screen) in accordance with them. The
Volvo Penta 7" Display can only be connected to
EVC-C3 and future versions.
NOTE! When installing several 7" Displays a PFM must
also be installed. Applies only to 12 V systems. Refer to
the EVC installation manual.
NOTE! Installation materials (nuts, washers and bolts)
are not included.
NOTE! Autoconfiguration must be performed the first
time the system is switched on, or after an update. Refer
to the installation manual.
NOTE! Contact an authorized Volvo Penta dealer to acti-
vate and configure the unit after installation.
Location and installation
- Decide on where to install the display.
IMPORTANT! In twin installations with two displays
at one or more helm stations, the displays must be
positioned such that the helmsman immediately
understands which engine (port/starboard) each
display belongs to.
- Try to keep cable runs as short as possible, to reduce
the risk of voltage drop and interference.
- All cables must be installed at least 300 mm away from
other cables carrying radio frequencies or pulsed sig-
nals.
- The underlying material must be flat and sufficiently
strong to withstand the weight of the display and protect
it from heavy vibrations or shocks.
- Check that there is sufficient room behind the unit for
connectors, so that cables need not be run with sharp
bends. Also make sure that there is sufficient cable to
allow the unit to be removed for service.
- Check that there is sufficient ventilation in the installa-
tion space, especially if the display is installed flush. The
operating temperature around the back of the display
(case) must not exceed 60 °C.
- Install the display in a location that is protected from
prolonged, direct exposure to rain and water splashes.
- The Volvo Penta 7" Display supports 1-4 drivetrain
units.
- As far as possible, protect the display from the harmful
effects of sunlight by making a habit of always replacing
the protective cover when the unit is not in use. Long pe-
riods of direct sunlight may cause functional faults in the
screen due to excessive heat.
Plus d'informations sur : www.dbmoteurs.fr
Alternative A - Top installation (installation with frame)
1. Position the hole template supplied at the location
Quantity Pos. in fig.
where the display will be installed. A full-size template is
1
1
located in the back of this installation instruction. Refer
1
2
to figure A.
1
3
1
4
NOTE! Cut-out (Fig. A) dimensions are only nominal and
1
5
should be cross-checked with actual physical dimen-
1
-
sions before cutting out takes place.
2. Drill and cut out the installation area with the aid of a
jigsaw along the inside of the line shown on the temp-
late. Drill the four holes for the attachment screws with a
3 mm drill. Refer to figure A.
3. Connect the harness to the back of the display. Refer
to figure 2 and the EVC installation manual.
4. Place the display in the cut-out and screw it securely
in position with suitable fasteners.
NOTE! For top installation, the use of screws with the
following head dimensions is recommended: MRX M4,
MRT M4, RXS B7, RTS B9, RXB B8, MFX-GF M4, MRT-
GF M4, TP 4.0, SPAX-KXTB 4.0 and STS T40 KN 1032.
5. Remove the protective film from the unit.
6. Place the plastic frame over the display and press it
into position. When the frame is in the correct position, a
light "click" will be heard from the integrated plastic clips
on the inside of the frame.
7. Fit the protective cover to the display.
NOTE! The protective cover must not be on when under
way.
Alternative B - flush installation:
NOTE! The thickness of the installation surface for flush
installation must be between 4-8 mm. Unit depth for
flush installation is 3.5 mm. A flush-mounting bracket is
not included in the kit.
1. Position the hole template supplied at the location
where the display will be installed. A full-size template is
located in the back of this installation instruction. Refer
to figure B.
NOTE! Cut-out (Fig. B) dimensions are only nominal
and should be cross-checked with actual physical di-
mensions before cutting out takes place.
2. Drill and cut out the installation area with the aid of a
jigsaw along the inside of the line shown on the temp-
late.
3. Connect the harness to the back of the display. Refer
to figure 2 and the EVC installation manual.
4. Remove the protective film from the unit.
5. Place the display in the cut-out and press it home.
When the frame is in the correct position, a light "click"
will be heard from the integrated plastic clips on the in-
side of the frame.
IMPORTANT! It is important that the correct screws
are used to fasten the display to the installation
surface. If the wrong screws are used, both the
display attachment and underlying material may be
damaged.

Publicidad

loading

Este manual también es adecuado para:

213302882185386621334200