Fitting inlet

On the inlet surface, an X is cut into the geo textile.
The inlet pipe is slid in around 20 cm (7,87") and
the rest of the X cut glued or welded to the pipe.
The vents needed are produced in the same way.
The vertically aligned vents can be produced on
the horizontal drill surface using a 90° KG bend
(plastic pipe bend).
7.6

Connecting inspection channel

The bases of the EcoBloc Inspect system can be
inspected and driven on. Please use the bottom
connections in the end plates of the EcoBloc
Inspect to connect the inspection channel
7.7

Covering the EcoBloc Inspect system

Before covering the installation, all inlets, vents
and shafts must be connected. Ensure that the
geo textile is not pulled apart.
remain in place when filling.
The EcoBloc Inspect system must not be
driven
over
directly
machinery.
When the trench is being backfilled, the installation
conditions described in Chapter 6.3 must be
observed and adhered to. Provided that the
installation situation does not require special
backfilling materials, the packed drainage system
is backfilled with coarse-grained, compressible
loose ground (gravel, crushed stone, sand etc.) at
least up to the top edge of the drainage system.
Above the top edge of the drainage system, any
excavated earth or similar can then be used for
backfilling the trench if necessary
larger stones or similar foreign objects should be
removed.
7. Installation
Overlaps must
with
construction
.
Sharp objects,