PREPARATION FOR AUTOMATION OF
THE BASE
1. Provide a foundation pit and arrange one or more conduits for
the passage of the electrical cabling.
2. Assemble the 4 anchoring brackets on the mounting plate and
fasten with the 4 bolts provided.
3. Pour the concrete into the inside of the pit and position the
base plate.
NOTE: verify that the plate is perfectly leveled and
parallel to the opening barrier.
4. Wait for the complete setting of the concrete.
5. Unscrew the 4 nuts that hold the base joined to the anchoring
brackets and position the rack on the plate.
NOTE: it is advisable to install the rack cabinet with the
inspection access flap turned towards the more
accessible side.