Design
The Multistore is delivered on a transport frame. For the installation on site, the customer shall provide expert
staff (two or four persons), as well as lifting equipment (fork lift or crane) and the appropriate tools.
Open the strapping and remove the packaging film,
-
Unscrew the fixing screws from
the base plate.
Drill dowel bores (ø12mm, 90mm deep) for the
-
ground anchors delivered as per drawing
Clean the boreholes
-
Remove nut and washer from the anchor
-
and insert the anchor in the borehole
Lift the Multistore and
-
place it carefully on the ground anchors
Align the Multistore
-
Place the washers and tighten the nuts
-
with a torque of T
inst
213141_BA_Multistore_002_INT
= 20 Nm.
M12