ENGLISH
1. Loosen all 6 screws (6) to remove the cover of the junction box.
2. Unscrew all input glands and remove the dummy cables that were originally installed.
3. Insert the cables in the glands
IMPORTANT
Make sure that the cable diameter corresponds to the min/max diameter of the
input glands to assure that the installation is waterproof. (check the specifications for more
information on cable diameters!) If one of the glands is not used you MUST install the original
dummy cable!
4. Make all necessary connections for both mains and DMX-cables.
5. Tighten the input glands well to be sure that they become waterproof.
6. Make sure that the rubber sealing is installed before closing the top cover again.
7. Fasten the 6 screws well to assure that the box is waterproof.
8. The junction box should be installed on a non-flammable flat surface, for an underground installation, the
junction box can be dug in as well.
SPECIFICATIONS
Power cables:
DMX signal cables:
Mains voltage:
Mains current:
Insulation resistance:
Glow-wire test enclosure:
IP-code:
Size:
Weight:
You can download the latest version of this user manual on our website: www.beglec.com
BRITEQ
®
3 input glands, for cable diameters ranging from 7mm to 11mm
4 input glands, for cable diameters ranging from 3mm to 6,5mm
< 300Vac
< 15A
> 100MΩ
650°C (according to IEC 60695-2-11)
IP68
see drawing
0,15 kg
All information is subject to change without prior notice
3/19
OPERATION MANUAL
LDP-JUNCTION IP68