Complete Installation

You have completed your panel installation.
For Onsite Factory Commissioning, call Lutron Technical Support and select Startup to schedule a field service
visit. Allow for 10 working days between day of call and scheduled visit.
If you purchased Telephone Startup (Softswitch128/XPS only), stop here and complete the Control Location,
Panel, and Control Station Tables that are located in the back of the Setup and Operation Manual. Once the
tables are complete, call Lutron Technical Support and select Startup. Please call 24 hours prior to desired
system startup.
In the U.S., Canada, and the Caribbean: 1.800.523.9466
In Mexico: +1.888.235.2910
In Europe: +44.207.702.0657
In Asia: +65.6220.4666
In Japan: +81.355.758.411
In all other countries: +1.610.282.6701

Remove Bypass Jumpers

A. After all load wiring has been checked, turn circuit
breakers OFF.
B. Remove and store the bypass jumpers for possible
future use.
C. Turn circuit breakers ON.
Caution! Reuse the bypass jumpers
whenever work is being done on a load.
Damage caused by short-circuits and
miswiring is not covered by the product
warranty.
Panel installation, control station wiring, and load activation are now complete.
Next Step: Refer to the Setup and Operation Manual to set up the functions and operation of the panel.
R
Extraction tool
Bypass jumper
Installation Guide for Switching Panels
17