7. MECHANICAL SAFETY
The hazardous points on the IMER plastering machine are pro-
tected by means of suitable safety devices, which must remain
fitted at all times and kept in perfect condition, such as the electric
motor cooling fan guard, the grid on the hopper to prevent contact
with the mixer
In particular, the opening of the motor support flange or removal of
the hopper grid causes shutdown of the rotary parts of the machine
thanks to a specific safety microswitch.
8. TRANSPORT
- CAUTION! Before moving the plastering machine,
always detach the power plug.
Before moving the plastering machine the water delivery hose and
material delivery line must be detached.
Only a minimal amount of the material should be in the hopper
when handling.
Release the wheel by means of the brake and move the mixer by
means of the handles (as shown in the figure below)
BRAKE
- CAUTION! Before lifting the plastering machine, always
disassemble the compressor for separate transport.
- CAUTION! Before lifting the plastering machine, always
check that all machine components are correctly secured
and fitted in place.
To lift the machine, use the two specific attachment rings on the
sides of the machine (as shown in the figure below)
IMER INTERNATIONAL S.p.A.
KOINE 3
RH LATERAL
RING
- CAUTION! Lift with care to avoid hazardous oscillations
- CAUTION! Never use points other than as specified in
figure 3 to lift the machine and in particular do not hook up
lifting equipment to the gearmotor guard.
Use lifting equipment suited to the overall weight of the machine
indicated in table 1.
To facilitate transport, the machine can be disassembled into the
motor unit, hopper unit and compressor.
9. INSTALLATION
Position the plastering machine on a flat surface in an area where
it does not constitute an obstruction either during use or cleaning
at the end of the work shift and where a minimum quantity of
pipelines is required.
Secure the machine in place by means of the wheel brake.
10. CONNECTIONS

10.1 ELECTRICAL CONNECTION

- Ensure that the power supply voltage, mains frequency
and electrical connection (socket, fuses, cable) correspond
to specifications in table 1.
The power supply line must be equipped with current overload pro-
tection (e.g. with fuses or a thermal cut-out) and protection against
current dispersion to ground (e.g. residual current circuit breaker).
The electric cable wire size must take into account the operating
currents and length of the line to avoid excessive voltage drops.
Avoid use of extension leads wound on drums. The power cable
must be suitable for frequent movements and with an abrasion
resistant sheath (e.g. type H07RN-F).
Before connecting the plastering machine to the electrical mains,
ensure that all safety devices are fitted and are in perfect con-
dition, and check in particular that the hopper grid is secured in
place, that the extension in good condition and that the plugs and
sockets are not wet.
Connect the plastering machine plug on the electrical panel to
the mains; the blue indicator light turns on to indicate power ON
(ref.2). If the blue light remains off, the voltage exceeds 240V.