Components List - Eden Blockley Manual Del Usuario

Ocultar thumbs Ver también para Blockley:
Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 22
Base
The integral base must be 100% level and square, the la er can be done by
checking the 2 diagonals are equal. If it is not square the glazing will not fit.
Construc on

COMPONENTS LIST

SECTION 0 FOUNDATION
SECTION 1 REAR GABLE
SECTION 2 FRONT GABLE
SECTION 3 SIDES
SECTION 4 ASSEMBLE
SECTION 5 ROOF
SECTION 6 WINDOWS
SECTION 7 DOOR
SECTION 8 LOCATING
SECTION 9 GLAZING
SECTION 10 FINISHING
For each sec on, lay the profiles out on the ground in the same way as pictured in the
main diagram. Assemble in the order of the pictures.
M6 x 10 bolts/nuts (parts 50 and 51) are not listed on individual parts lists as they are
used in each sec on.
The following symbols show whether an illustra on is viewed from inside or outside
the greenhouse:
Viewed from the inside
(White background)
#
Page 2
GB - Introduction
Take note of where you will need to slide extra bolts into the
channels for fixing horizontal bars, bracing or roof vent sills as
per example picture to the right.
Fasten the profiles together by sliding the square headed bolts
into the channel of the profile and a ach to the hole in the
corresponding bar. Do not ghten the nuts completely un l the
completed frame is square. NOTE THAT ALL CONNECTING PROFILES MUST BE FLUSH
AND TIGHT TOGETHER TO ENSURE THAT LEAKING IS KEPT TO A MINIMUM.
The door has a zero threshold™. Component 78 at the base of the door on the front
gable (SECTION 2 FRONT GABLE) is used as a brace to gauge the distance between the
two components 18 and to make construc on easier. This will then be removed in
SECTION 10 FINISHING.
Glazing
Glazing must be completed in one opera on. Fit the rubber glazing gasket to all the
profiles as shown in SECTION 9 before fi ng the glass. Note there are 3 different plans
for glazing: hor cultural glass, toughened glass or polycarbonate. Glaze the roof first,
then sides and gable ends. Glaze roof vents before sliding in from THE END of the
ridge bar as shown in SECTION 10 FINISHING. Glaze the door before hanging as
shown in SECTION 7 DOOR.
Finishing Touches
Fit all plas c parts, i.e. Ridge Cap, Gu er End Caps and Integral Base Corner Caps by
pushing into place as in SECTION 10 , FINISHING.
Note: Fit Integral Base Corner Caps before securing down the greenhouse.
Maintenance
Viewed from the outside
(Black background)
#
Eden Greenhouses Customer Helpline: +44 (0)1242 676625
The door sliders and lock will need to be lubricated approximately every 6
months with an OUTDOOR lubricant to ensure smooth opera on.
The gu ers will need to be regularly cleared of leaves and debris to ensure
efficient drainage.
Replace all broken panes of glass immediately, failure to do so may cause
structural failure.
Remove snow loads from the roof.

Publicidad

Tabla de contenido
loading

Tabla de contenido