ASSEMBLY AND OPERATION
This kit is intended for use on A-ipower lnverter
Generators.
Please refer to your Inverter Owner's Manual forsafety
rules, start up and shut down procedures,specifica-
tions and troubleshooting.
Set up and Operation(Applicable To All Models)
1. Align the two inverters on a firm, flat and level
surface at a minimum 20 inch apart.
WARNING
If not spaced apart, the exhaust heat
from one generator discolors or melt
the plastic shell on other generator.
lf not spaced apart, the exhaust heat from one unit
may discolor or melt the plastic on the other unit.
2. Inverters to be TURNED OFF and all electrical loads
DlSCONNECTED before installing parallel kit.
NOTE: Do not connect or disconnect the parallel kit
while the inverters are running.
3. The low idle switch(button) must be in the same
position (ON or OFF) on both generators.
20"
4. On each inverter:
4.1 Remove the parallel outlet covers. Plug the black
and red parallel cable terminals to the black and red
parallel outlet (black to black and red to red) on
each corresponding inverters control panel. Do not
plug two red cables or two black cables into the
same inverter.
4.2 Loosen nuts on grounding terminals and attach
round wire to ground terminal in each inverter.
Tighten securely.
Parallel Outlets
Grouding Wire
5. Turn on both inverters. See inverter owner's manual
for starting instruction.
Recoil start
Pull recoil starter slowly until resistance is felt,
then pull rapidly.
NOTE: Make sure the indicator light of overload reset
button(or output indicator) is green on each inverter.