4.2
Installation
1. Move the machine (and the accessories) to its final location.
Note:
Allow ample working space. See Figure 8.
Figure 8: Working space.
L = Maximum board length, S = Minimum space 60 cm.
2. Turn down the four leveling feet until the castors are off the floor.
3. Remove all transport material.
•
Cut the straps around the shaft suspensions and remove the foam pads.
•
Cut the straps holding the in-feed table arms
•
Cut the straps around the main roller axis and move up the top main roller to
remove the transport blocks from the nip.
•
Cut the straps holding the upper pull roller and open the pull rollers to remove the
transport plates.
4. Put a spirit level on the upper main roller and level the machine by adjusting the four
leveling feet.
CAUTION:
Check the mains values before connecting. See section 3.4 for power supply
details
5. Connect the machine to the mains using the power cable supplied with the machine.
CAUTION:
Only if absolutely necessary, use an extension cable of ample capacity.
Unroll the extension cable completely.
WARNING:
MAKE SURE THE POWER SUPPLY CABLE AND/OR THE EXTENSION
CABLE IS NOT BLOCKING YOUR WAY AROUND THE MACHINE.
Installation
MyBinding.com
5500 NE Moore Court
Hillsboro, OR 97124
Toll Free: 1-800-944-4573
Local: 503-640-5920
19