Installation; Installation Site; There Must Be Ground Drainage; Ventilation And Aeration - BADU BNR 400 Instrucciones Para El Manjeo

Tabla de contenido

Publicidad

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 166

Installation

5
Installation
5.1

Installation site

5.1.1
Installation
The installation site must be clean and dry. Installation
outdoors is not permitted.
The installation position is flexible, display and switch must
be operable.
5.1.2

There must be ground drainage

Calculate the size of the ground drain according to the
following criteria:
– Size of the swimming pool.
– Circulation flow rate.
– Flow feed
5.1.3

Ventilation and aeration

Ensure sufficient ventilation and aeration. The ventilation and
aeration must ensure the following conditions:
– Prevention of condensation.
– Limitation of the ambient temperature to maximum 40 °C.
5.1.4

Reserve space

Measure reserve space so that the upper part of the
BADU OmniTronic can be removed and the clock can be set
without any trouble. Observe a removal height of 200 mm.
5.1.5

Cable laying/line laying

Voltage potentials must be separated as shown in the
following drawing.
Use line/cable laying as shown in the following drawing.
20 EN
01|2020

Publicidad

Tabla de contenido
loading

Tabla de contenido