Installation
5
Installation
5.1
Installation site
5.1.1
Installation
•
The installation site must be clean and dry. Installation
outdoors is not permitted.
•
The installation position is flexible, display and switch must
be operable.
5.1.2
There must be ground drainage
Calculate the size of the ground drain according to the
following criteria:
– Size of the swimming pool.
– Circulation flow rate.
– Flow feed
5.1.3
Ventilation and aeration
Ensure sufficient ventilation and aeration. The ventilation and
aeration must ensure the following conditions:
– Prevention of condensation.
– Limitation of the ambient temperature to maximum 40 °C.
5.1.4
Reserve space
Measure reserve space so that the upper part of the
BADU OmniTronic can be removed and the clock can be set
without any trouble. Observe a removal height of 200 mm.
5.1.5
Cable laying/line laying
Voltage potentials must be separated as shown in the
following drawing.
Use line/cable laying as shown in the following drawing.
20 EN
01|2020