7
Service and Maintenance
Engineers Forms
Commissioning/Field settings record sheet (continued from the previous page)
Main controller screen
Service menu
Heat source setting
Operation settings Freeze stat function Outdoor ambient temp. (3 - 20°C)
External input
settings
*3 When Dip SW1-1 is set to OFF "WITHOUT Boiler" or SW2-6 is set to OFF "WITHOUT Mixing tank", neither Boiler nor Hybrid can be selected.
*4 On: the function is active; Off: the function is inactive.
*5 "*" of "*/kwh" represents currency unit (e.g. € or £ or the like)
Parameters
Standard/Heater/Boiler/Hybrid *3
Simultaneous
On/Off *4
operation (DHW/
Heating)
Outdoor ambient temp. (−15 - +10°C)
Cold weather function On/Off *4
Outdoor ambient temp. (−15 - −10°C)
Room temp control
Temp. control interval (10 - 60 mins)
(Heating)
Flow temp. range
Heat pump thermo diff.
adjust
Boiler operation
Hybrid settings
Intelligent settings
Floor dry up function
On/Off *4
Target temp.
Flow temp. (Increase)
Flow temp. (Decrease) Temp. decrease step (−1 - −10°C)
Demand control
Heat source OFF/Boiler operation
(IN4)
Outdoor thermostat
Heater operation/Boiler operation
(IN5)
Min. temp. (25 - 45°C)
Max. temp. (35 - 60°C)
On/Off *4
Lower limit (−9 - –1°C)
Upper limit (+3 - +5°C)
Outdoor ambient temp. (−15 - +10°C)
Priority mode (Ambient/Cost/CO
2)
Energy price
Electricity (0.001 - 999 */kWh) 0.5 */kWh
*5
Boiler (0.001 - 999 */kWh) 0.5 */kWh
CO
Electricity
2
emission
(0.001 - 999 kg -CO2/kWh)
Boiler (0.001 - 999 kg
-CO2/kWh)
Heat source
Heat pump capacity
(1 - 40 kW)
Boiler efficiency
(25 - 150%)
Booster heater 1 capacity
(1 - 20 kW)
Booster heater 2 capacity
(1 - 20 kW)
Start&Finish (25 - 60°C)
Max. temp. (25 - 60°C)
Max. temp. period (1 - 20 days)
Temp. increase step (+1 - +10°C)
Increase interval (1 - 7 days)
Decrease interval (1 - 7 days)
Default
Field
Notes
setting
setting
Standard
5°C
Off
−15°C
Off
−15°C
10 mins
30°C
50°C
On
−5°C
5°C
−15°C
Ambient
0.5 kg -CO2/kWh
0.5 kg -CO2/kWh
11.2 kW
80%
2 kW
4 kW
Off
30°C
45°C
5 days
+5°C
2 days
−5°C
2 days
Boiler
operation
Boiler
operation
58