7.5
Fitting inlet
On the inlet surface, an X is cut into the geo textile.
The fitting around inlet is slid in around 200 mm
(7.87") and the rest of the X cut glued or solvent
weld to the pipe.
The vents needed are produced in the same way.
The vertically aligned vents can be produced on
the horizontal drill surface using a 90° bend (plastic
pipe bend).
7.6
Connecting Inspection channel
The bases of the EcoBloc Inspect system can be
Inspected and driven on. Please use the bottom
connections in the end plates of the EcoBloc
Inspect to connect the Inspection channel.
7.7
Covering the EcoBloc Inspect system
Before filling the installation, all inlets, vents and
shafts must be connected. Before backfilling
ensure that the geotextile is not pulled apart.
Overlaps must remain in place when filling.
The EcoBloc Inspect system must not be
driven
over
directly
machinery.
Fill the sides of the EcoBloc Inspect installation
with gravel (grit 8mm/16mm) (0,31"/0,63") at least
up to the top edge of the EcoBloc Inspect system.
Above the top edge, the excavated soil can be
used to cover the EcoBloc Inspect system.
7. Installation
with
construction
26 / 60