Commissioning
Commissioning
Proceed step by step:
48
Switch on the mains
Observe status display
After a short initialisation time, the display must be blinking green.
Set controller enable
After the set starting time, the motor must rotate with the set speed.
First check of the expected behaviour:
- Direction of rotation?
- Starting time?
- Speed?
- Speed control?
Check of optional control functions:
- Does the analog setpoint selection work?
- Do the digital control signals, e.g. limit switches, work?
- Does the change of direction of rotation work?
- Do the control signals over fieldbus work?
Switch off drive
- Reduce speed
- Inhibit controller enable
- Switch off
mains
Commissioning
CDN40-xxx, DE/EN/FR/ES/IT
7