Level
5. Mark the Wall Jamb Locations
Position a wall jamb against the wall directly over the bottom track. The wall jamb should sit flat
against the wall.
Slide the wall jamb down over the bottom track until the wall jamb and bottom track are fully
engaged.
NOTE: The wall jamb must sit flat on the bottom ledge. If your ledge has a curve in the corners at the side
wall, it may be necessary to shape the bottom end of the wall jamb with a file.
Use a level to plumb the wall jamb vertically.
Using the pre-drilled screw holes as a guide, mark the hole locations on the wall.
Repeat the procedures with the second wall jamb.
Remove the bottom track and wall jambs.
NOTE: When installing on ceramic tile, use a center punch to nick the surface of the glaze. Tap the center
punch lightly with a hammer to avoid cracking the tile.
Lightly center punch the hole locations.
Drill a 3/16" hole at each mark. Use a tile or masonry bit for ceramic tile.
Thoroughly clean the shower floor ledge and wall.
Insert plastic anchors in each hole.
Sterling
Anchor
Pencil
Wall
Jamb
7
If necessary, shape
bottom end of wall jamb.
Bottom
Track
Wall jamb fully engaged
with bottom track
1034033-2-B