Installation and tensioning of the cable.
This instruction is applicable to the following series of article numbers:
NAT822, NAT824, NAT825, M87201, M87202, M88101, M88102, M88111, M88112,
NRO801, NRO874
Preparation:
Unwind the cable from the start station to the end station to avoid twists and hitches. Please
put the cable end in the top element of the start station ( AC260206-99 ) like is mentioned on
detail 2 and install the 3 iron grips (OBV-5412000) according to detail 2.
Please install on cable the following parts in the following sequence (Detail 1):
Shock buffer with flange (OKU-STB1205)
Shock buffer (OKU-BUF1205)
Trolley (AC260213-99, AC260211-99 - US ONLY)
Please make sure to avoid sand from entering the trolley by putting the trolley on plastic.
Spring (AC260215-99)
Installation:
Please put the free cable end into the end station and tighten the cable manually to make sure
that the cable hangs 1.5 meter free from the ground and not higher!
Install now an iron grip (OBV-5412000) tight to the top element and tighten the bolts with 70Nm.
Install now the second iron grip on a 5 cm distance and tighten the bolts also here.
Tension the cable for the first time: no load on seat.
Please tension the cable by using the tensioning device (OME-2227575). Please see detail 3.
Please tension the cable in such a way that the free space between bottom side of the
seat and the ground level is 67 cm on the lowest point of the cable hanging. This point is
situated approx. 4 meter from the top element of the end station AC260206-99.
Please install 3 the iron grips (OBV- 5412000) according to deta il 3.
Copyright©KOMPAN A/S
41/68