Commissioning
Commissioning single unit
System with one inverter
Single device
40
NOTE
For a better understanding of keyboard operation, please also see the chapter Ope-
ration.
The procedure for commissioning the inverter as a
x single unit
x and as a master and slaves with several networked units
is described in detail below.
1.
The commissioning process starts with setting of the display language. Select
the language in selection menu with
Confirm the selected language with
2.
Select the country in the selection menu with
3.
Confirm the country of installation with
NOTE
The inverter only starts feeding current into the grid once the country has been se-
lected.
4.
Select "Single unit" in the selection menu with
Confirm with
.
5.
Set the date and time.
Select date with
. Change the selected number with
the next number with
Confirm the date with
/
.
.
/
.
/
/
.
and set the time accordingly.
.
.
/
and jump to