Stone Bedding; Installing The Supporting Braces - BWT myPOOL POOL'N BOX Instrucciones De Montaje

Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

5.2.4 Stone bedding

Level the floor of the excavation as much as possible, and then roll out the geotextile to cover the entire floor.
Using 20/40 mm gravel lay hardcore to a depth of 110 mm around the entire periphery of the excavation.
Correct tamping of the gravel will ensure a neat finish of the excavation floor, and facilitate installation of
the supporting braces.
Remove the gravel at the positions shown in
90 mm deep (as measured from the surface of the stone bedding). The recesses will accommodate the
steel braces, once imprisoned in the concrete, these braces will support the pool structure
5.3

Installing the supporting braces

Install the supporting braces in each of the four locations, having first fitted the recesses with jacks
(Figure
3). Use 4 double acting jacks,4 single acting jacks and 24 screws with a diameter of 10 mm (bag
A). The top screws should be inserted after the height of the bottom screws has been adjusted.
The supporting braces must under no circumstances extend above the top of the pool wall (just
beneath the coping) after adjustment of the supporting brace jacks. On the contrary, it is not problematic
if the top of the supporting braces are 1 or 2 cm below the top of the pool wall.
14/48
2021/02 - Version: D Code : 37311
Figure 2 – Positions of the recesses created to accommodate the supporting braces
Figure 3 – Installation of the jacks under the supporting brace
Figure 2
in order to create four 500 × 650 mm recess
WOODEN POOLS
BWT myPOOL POOL'N BOX

Publicidad

Tabla de contenido
loading

Tabla de contenido