C
Figure 7. Routing Heater Wires (11-22kW)
5.
See
Figure
8. Pass the lead wires through the customer
connection panel grommet (D). If the empty Y-harness
socket (E) will not be connected to a battery heater, coil the
wires and secure with a plastic wire tie. Secure all wires with
plastic wire ties at least 0.5 in. (1 cm) away from fuel hoses.
E
Figure 8. Lead Wires to Customer Connection (11-22kW)
6.
Proceed to
Connecting Lead

Connecting Lead Wires

2016 and Newer Units—
See
Figure
9. Connect the lead wires to the 240 VAC Input
Sense terminals N1 and N2 as shown.
Figure 9. Input Sense Terminal Block
Part No. 10000003502
Rev B 07/14/17
©2017 Generac Power Systems, Inc.
All rights reserved
Specifications are subject to change without notice.
No reproduction allowed in any form without prior written consent from
Generac Power Systems, Inc.
002826
D
002780
Wires.
002781
NOTE: It does not matter which lead wire goes into N1 or N2.
2013-2015 Units—
See
Figure
10. Connect the lead wires to the 240 VAC Input
Sense terminals N1 and N2 as shown.
Figure 10. Input Sense Terminal Block
NOTE: It does not matter which wire goes into N1 or N2.

Completing Installation

Engine damage. Verify proper type and quantity of
engine oil prior to starting engine. Failure to do so
could result in engine damage.
1.
Verify all wire routings are clear of pinch points and other
damage. Use tie wraps where necessary.
2.
Install customer connection panel cover.
3.
Return the utility power supply to the transfer switch:
• For service rated transfer switches, turn the main breaker ON.
• For non-service-rated switches, turn power feeder breaker ON.
4.
If removed, install the T1, N1 and N2 fuses in the transfer
switch.
5.
Install controller fascia (2013–2015 units) or intake side
panel (2016 and newer units), front panel, and 7.5A DC
fuse.
6.
Complete the installation wizard programming.
7.
Move the main line circuit breaker (generator disconnect)
to ON (closed).
8.
Place the generator controller in AUTO and close lid.
CAUTION
Generac Power Systems, Inc.
S45 W29290 Hwy. 59
Waukesha, WI 53189
1-888-GENERAC (1-888-436-3722)
www.generac.com
002887
(000135)

Publicidad

Tabla de contenido
loading

Tabla de contenido