Commissioning
Combination elec-
trode F 800
Double rod elec-
trode
F 500 + R 503
20
Commissioning
1
Remove the storage vessel.
2
Fill the bridge electrolyte ELY/BR/503 into the filling opening.
3
Shortly press the shaft of the combination electrode against the con-
nection head to wet the ground junction with bridge electrolyte.
4
When doing so refill any spilled bridge electrolyte so that the inner
junctions are covered with bridge electrolyte.
5
Rinse the combination electrode with deionized water.
6
Wipe the shaft using a clean paper towel.
For measurements with the F 500 electrode, a reference electrode is re-
quired (e.g. R 503). The two electrodes together form a double rod combina-
tion electrode.
1
Put the reference electrode into operation (see operating manual of
the reference electrode).
2
Remove the protection cap of the electrode.
3
Rinse the electrode with deionized water.
4
Wipe the shaft using a clean paper towel.
F 500 / F 800
ba15358e03
03/2015