CONCRETE BASE
INSTALLATION OF POOL ON CONCRETE FLOOR
B
1
Important:
In the case of being non-stable land, we recommend to make a concrete slab instead of a bed of sand.
The bag should be perfectly flat and smooth, to avoid any imperfection
1- Surrounding area
2- Concrete slab
The concrete slab is not included.
Dosing 350 kg/m
(standardized type C125 430)
3
Ref. KPBRC420
L: 5,20 x W: 3,20 x H: 0,15 m - 2,5 m3 concrete.
The floor should be perfectly horizontal and flat.
Lightly draw a rectangular surface according to the dimensions indicated in the table.
Before pouring the concrete, the structural system (columns and internal structure, beams) should be perfectly levelled),
After building the structure, the framework can be placed over it.
Make sure that the structure is well fixed to avoid its movement when pouring the concrete. The base of the structure
should be completely covered, with 2 cm of concrete over the PEAO base.
If you are going to use a concrete slab, the flanges should not be installed (AP).
B
INSTALLATION ON CONCRETE SLEEPERS
2
Always that the terrain is stable, you can build concrete sleepers. This way, there is no need to build a complete concrete
slab as indicated in point B1. You will need less time to build the sleepers and will save a considerable amount of concrete.
If you are not sure about the stability of your terrain, we recommend that for safety reasons, you build a complete concrete
slab.
H
We recommend to ask a
professional to prepare the
foundation slab.
Y
300cm
C
.
70 cm
1
70 cm
3726 mm
50 cm
70 cm
C
Columns
59
Ref. KPBRC420
5200 mm
90°
2
Y
Sleepers

Publicidad