A central controller with an output signal
between 0 - 10 V (e.g. a PC) and a power
add-on RE-LT6.
•
A modulating temperature controller RE-
THA6.
For operation and adjustment of the
modulating controller, please contact your
dealer.
2.8
Power add-on RE-LT6
A
Rotary switch:
-
AUS: Off
-
DAUER: Maximum capacity
-
AUTOM: Modulating control
B
Setting minimum value
C
Setting maximum value
D
Indicator light
2.9
Temperature controller RE-THA6
(fig. 13)
A
Tumbler switch:
-
I: Modulate
-
0: Off
-
II: Maximum capacity
B
Indicator light, green
C
Digital reading
D
Setting the desired temperature
E
Setting the band width modulation
F
Pushbutton for temperature setting
G Setting maximum capacity
H
Setting room thermostat limiter
I
Indicator light, orange
J
Setting alarm maximum capacity
K
Alarm light
L
Indicator light, red
M Setting alarm minimum capacity
N
Setting minimum capacity
2.10
Accessories
•
Room thermostat
•
Pre-pressure regulator
•
Outside air suction hose
•
Outside air feed-through
18
3
3.1
1. Remove packaging from the heater.
3.2
1. Make sure that the heater has a stable
set-up.
(fig. 12)
2. Hang the heater on the suspension eyes.
3. Fit a gas cock with an internal
screwthread of 3/4" to the gas inlet of the
heater, see fig. 7 (A).
4. Connect the heater to the gas supply.
5. Shut the gas cock off and place the gas
pipe under pressure.
40.020.954 - rev. 05 - 2017
PREPARATIONS
Removing the packaging
Installation
The heater can be positioned both
horizontally and vertically (blowing up
or down).
•
Horizontal: a minimum of 0.5 m
above the floor.
•
Vertically blowing down: a
minimum of 1.4 m above the
floor.
•
Vertically blowing up: a minimum
of 1.4 m below the ceiling.
The position of the gas regulator
block depends on the heater set-up,
see fig. 6.
Warning
The heater is suitable for a gas
pressure of up to 100 mbar
(maximum operating pressure AGA
102 is 50 mbar).
When connecting to a higher gas
pressure, a pre-pressure regulator
must be included in the gas pipe,
see(fig. 7) (B).
Warning
The heater may only be connected
by suitably authorised people in
accordance with the local standards.
AGA 100/102