Step 7: Preparing the tank
a
Turn the tank on its side.
b
Apply the foam tape to the bottom of the tank, around the outside edge (in the recessed channel shown in red below).
c
Lift the tank and carefully position it over the vertical water supply line.
d
Attach the ½ inch flex line to the shut-off valve and then attach the valve and mount assembly to the tank.
Step 8: Installing an immersion heater (optional)
a
Inside the tank, slide the 250 W immersion heater under the float.
b
Feed the electric cord through the access cavity.
c
With the panel door open, plug the immersion heater into the electric service, next to the ½ inch flex line.
Step 9: Filling the tank
a
Insert the drain plugs on both sides of the tank.
b
Turn on the water supply to fill the tank and check for leaks. If no leaks are found, attach the float reservoir lid.
Step 10: Affixing the tank to the concrete slab
a
Drill ½ inch holes in the concrete using the mounting feet located on each corner of the tank as a guide.
b
Insert anchor bolts in each hole. Place washers over anchor bolts, then apply the nut. Tighten the nut and repeat on all
four corners so that the WaterPro2 is securely mounted.
c
We recommend caulking the perimeter of the tank to protect it from wind and debris.
13