P30 Installation Guide
The UPS (
the UPS into the rack.
NOTE
6
9.
Align the mounting brackets (provided in the rack mounting bracket kit) with the
screw holes on the side of the UPS and secure with the supplied #6-32
screws (see Figure 5).
10.
If installing an optional EBM, repeat Steps 7 through 9 for each cabinet.
Mounting
Handle
EBM (93
81.5 lb/37 kg) and
The EBMs must be installed below the UPS as shown in Figure 6.
11.
Slide the UPS and any optional cabinets into the rack.
12.
To secure the back of the UPS to the rack, loosen the wing nut on the rear hold-down
bracket and slide the bracket over the rear of the UPS. Tighten the wing nut.
®
Powerware
9125 (9910 P30) Installation Guide for IBM
Figure 5. Installing the Mounting Brackets
C A U T I O N
are heavy. A minimum of two people are required to lift
lb/42.5 kg)
Figure 6. Installing the UPS
Figure 7. Securing the Back of the UPS
Applications S 164201544 Rev A Final 29-Jun-2004
®
×
3/8" flat-head
Mounting
Bracket
Rear Hold-Down
Bracket