Caution: align the holes in parts C63 and D43 with the holes in the CB6, CB7 and CL9 balusters
(Fig. 7)
16. Insert the CB6 balusters into F23 elements, positioning C63 element with the open part towards
the top, locking them with element B02. Secure element F34 to the floor, next to the first baluster
CL9 and drill using a Ø 8 mm bit. Use elements B12, B02, C58. Insert the CL9 baluster and
tighten element B02. Check the verticality of each baluster. Starting from the baluster at the top,
secure the A22 handrail (leave the amount of handrail required to secure baluster CB6, which
goes at the end and has not been inserted yet) using articles C64 and an electric screwdriver.
Join the handrail A22 elements to articles B33 and D72 using the X01 glue. Saw off the excess
handrail next to the first and last baluster using a hacksaw and complete assembly by inserting
element A37 using article C64 and X01 glue (fig. 1).
17. Insert the steel cables F.31 into items BG1 present on the balusters. Lock the cables at one of
the two ends with items D40 and C76, leaving around 15mm of the cables protruding from the
items BG1. Tighten the cables by hand and lock them with items D40 and C76. Cut off the cables
at a distance of 15 mm from item BG1. Fit part D38 at the end of the bar and tighten it with part
C76 (Fig. 1)
Caution: when cutting the cables we advise wrapping the cable end with adhesive tape so as to
avoid the cable unraveling. Use suitable shears.
Final Assembly
18. Verify that the whole staircase is vertical, and if necessary adjust it by moving support N16 (fig. 1).
19. Detach the first step L40 and, using a Ø 14 mm bit, drill holes in the floor in line with the holes in
support N16 (fig. 1).
20. Insert components C39 and permanently tighten them (fig. 1).
21. Replace the first step L40.
22. To further stiffen the staircase, fasten parts F09 to the wall and join them to the CB6 balusters
using parts F08. Drill using an 8mm Ø bit and use parts C50, C49, C58, B12 (Fig. 1)