3. FLARING WORK AND PIPE CONNECTION

3-1. FLARING WORK
remove burrs in order to avoid to let burrs drop in the piping.
on pipe having completed burr removal. (Not possible to put them on
shown in the table. Select A mm from the table according to the tool
Pipe diameter
Nut
17
22
26
29
3-2. PIPE CONNECTION
cause refrigerant leakage.
Outdoor unit connection
Connect pipes to stop valve pipe joint of the outdoor unit in the same
manner applied for indoor unit.
• For tightening, use a torque wrench or spanner and use the same
tightening torque applied for indoor unit.
WARNING
When installing the unit, securely connect the refrigerant
pipes before starting the compressor.
3-3. INSULATION AND TAPING
unit.
• When piping have to be arranged through above ceiling, closet or
All manuals and user guides at all-guides.com
for R410A
for R22
0 to 0.5
1.0 to 1.5
-
-
Good
Copper
pipe
Fig. 1
Copper pipe
Burr
Spare reamer
Pipe cutter
Fig. 3
Smooth all
around
Copper pipe
Die
Flare nut
Fig. 5
Tightening torque
N•m
for R22
13.7 to 17.7 140 to 180
1.5 to 2.0
34.3 to 41.2 350 to 420
49.0 to 56.4 500 to 575
2.0 to 2.5
73.5 to 78.4 750 to 800
No good
Tilted
Uneven Burred
Fig. 2
Flaring tool
Fig. 4
Inside is shin-
scratches.
Even length
all around
Fig. 6
kgf•cm
ft·Ib
10 to 13
25 to 30
36 to 42
54 to 58
7

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

Mxz-3b30naMxz-4b36na

Tabla de contenido