Open connection area
↻ Component is securely installed on the inverter.
1 Set the DC switch to the "OFF" position.
2 Unfasten the cover with lever via the 4 screws [
3 Remove cover and place back in the packaging.
4.2
Making the electrical connections
NOTE
Select conductor cross-section, safety type and safety value in accordance with the following basic condi-
tions:
Country-specific installation standards; power rating of the device; cable length; type of cable installation;
local temperature
Detailed information on tightening torques: See comprehensive operating instructions under
ergy.com/de/downloads
4.3
Configuring the DC cable
↻ DC cables inserted through the input plate.
↻ CAUTION! Risk of fire due to chemical corrosion. Cable lugs must be suitable
for the conductor material and copper busbars being used .
↻ WARNING! Risk of short circuit due to incorrect size of the cable lug! Observe
the dimensions for the selection. [See figure 4] [} Page 73]
1 Fit the DC cables with a ring cable lug. When crimping, ensure that the ring ca-
ble lug is rotated in accordance with the final installation position. [See figure
5] [} Page 73]
WARNING! Danger to life due to a surge in voltage. If the clearance is insuffi-
cient, shrink tubing (>= 6 kV/mm dielectric strength) must be used.
F Guide the shrink tubing over the uninsulated crimping point and a maximum of
+0/-2
20
mm over the cable insulation and shrink-fit using manual shrink-fitting
equipment.
F Draw in cables to the indicated fixing length and run with cable fitting.
ð DC cable configured. Continue with the connection to DC switch.
4.4
Connecting the DC cable to the component
Connecting the DC cable to the DC switch
NOTE: For installation of the DC cables, use a torque wrench as well as the in-
cluded open-ended wrench for counter-resistance.
1 Pre-fit DC cable pair with the pre-installed screw and counternut onto the DC+
and DC busbar of the DC switch.
2 Option for 2 cable pairs: Insert spacer sleeve between 2 DC cables and pre-as-
semble in pairs with the provided screws and counternuts onto the DC+ and DC
busbar of the DC switch.
3 Slide the DC input plate up onto the housing base and secure. [
Nm ]
4 Secure the screws and counternuts onto the DC+ and DC busbar of the DC
switch. [
W_16/17] /
5 Tighten the cable screw fitting. [
» The device is connected to the PV generator.
DC-Breaker
T_25]
30 Nm ]
W_46 /
10 Nm ]
Fig. 3: Open connection area
http://www.kaco-newen-
Ø 11 mm
3
Fig. 4: Configuring the DC cable
1
Cable lug
2
Shrink tubing*
3
DC cable
Option
T_30 /
6
Fig. 5: Fit DC cables to switch
1
Nut
2
Lock washer
3
Spacer sleeve
4
Fixing screw
max.
1.65
inch
2
1
1
2
4
1
2
3
4
Page 73