Puller Operation (cont'd)
Wire Pulling up to 6000 lb (26.7 kN) with
Main Capstan
1. Fish the rope through the conduit.
2. Set up the cable puller's boom. Refer to the illustra-
tions and instructions in the "Nose Operation" and
"Boom Operation" sections.
Set up the cable puller so that the rope will approach
the capstan at an angle of 90° (±5°). Angles outside
of this range may cause the rope to overlap.
90° (±5°)
3. Set up the anti-overlap guide arm and rope ramp as
shown:
a. Feed the rope between the pegs of the anti-
overlap guide arm.
b. Wind several wraps of rope around the main
capstan.
4. Plug the puller into a 20 amp grounded outlet.
Turn on the power switch/circuit breaker.
Greenlee Inc.
5. The lights will cycle through a power up sequence
with only the "0" light remaining lit. The default
startup speed is high. The high speed light will be
lit. To change the speed to low, double tap the foot
switch. The low speed light will illuminate. Double
tap the foot switch again to change back to
high speed.
MAIN
SECONDARY
6000
1750
5400
1575
4800
1400
4200
1225
3600
1050
3000
875
2400
700
1800
525
1200
350
600
175
0
0
PULL FORCE (LBS)
LOW
HIGH
SPEED
SPEED
DOUBLE TAP
FOOT SWITCH
TO CHANGE
THE SPEED
High Speed
Note: Force gauge indicator lights are for reference
only and should not be interpreted as precise
measurements of force.
6. After the foot switch is depressed, the green light
indicating 0 lb will be lit. As the force climbs, an
additional light illuminates for every 600 lb increase
in pulling force.
35
4455 Boeing Dr. • Rockford, IL 61109-2988 USA • 815-397-7070
G6 Turbo™
MAIN
SECONDARY
6000
1750
5400
1575
4800
1400
4200
1225
3600
1050
3000
875
2400
700
1800
525
1200
350
600
175
0
0
PULL FORCE (LBS)
LOW
HIGH
SPEED
SPEED
DOUBLE TAP
FOOT SWITCH
TO CHANGE
THE SPEED
Low Speed