PRELIMINARY INSTRUCTION (Model SAP-C)
When you install the coffee machine for the first time:
1.
Connect the tube provided with the machine to the water
supply net.
2.
Fill the boiler by pressing the water load button, placed on
the front of the coffee machine (represented by the icon) and the water
will beguin to fill the boiler.
Stop pressing the buttom when a certain intermediate water level
(that can be observed in the level indicator) is reached.
3.
Check that the working voltage and frecuency of the
machine (220 V, 50 Hz) are identical with those of your local power
supply.
4.
Before connecting the machine to the power supply, set
the main power switch to position 0.
5.
Connect the machine to the power supply, following the
instructions detailed in the electric
sketch.
6.
Change the main power
switch to position 1, a green led
will light (indicating the coming into
operation), and a red pilot will light,
indicating that the heating elements
are beginning to work.
7.
For each group, press one
of the pour buttons to eject the air
from the hydraulic circuit.
PRELIMINARY INSTRUCTION (Model EP-C and Model SAP-C
with automatic level control)
When you install the coffee machine for the first time:
1.
Connect the tube provided with the machine to the water
supply net.
2.
Check that the working voltage and frecuency of the
machine (220 V, 50 Hz) are identical with those of your local power
supply.
3.
Before connecting the machine to the power supply, set
the main power switch to position 2.
4.
Connect the machine to the power supply, following the
instructions detailed in the electric sketch.
5.
If the machine has been connected to the power supply
with the main power switch in position 2, a green led will light, the water
load valve will activate, and water will begin to fill the boiler to a minimun
level that can be observed in the level indicator.
6.
Once this minimun level has been achived, a security
alarm will trigger, and the dosing push-button leds will begin to blink. (Only
EP-C model)
7.
After this, set the main power switch to position 0, and all
the leds will stop blinking. Change then the main power switch to position
1. The machine will continue loading water in the boiler until a certain
intermediate water level is reached. The red pilot will light, indicating that
the heating elements are beginning to work.
8.
For each group, press the pour control buttons to eject the
air from the hydraulic circuit.