After wiring
What to check after wiring
Once actuator wiring is completed, please check the following:
1. Make sure that power supply voltage matches information on
the sticker on the side of the actuator.
2. Check that all connectors or cable glands are correctly
tightened.
3. Manually drive the valve to a mid-travel position.
4. Electrically operate counterclockwise rotation and check
that the motor rotates in the right direction.
5. Manually press on the counterclockwise end position switch
then the motor should stop.
6. Repeat steps 4 and 5 for clockwise direction.
If any fault is detected at this stage, please check that your wiring is correct.
4.5
Heating resistor
Each actuator includes a heating resistor.
As soon as the actuator is installed in the field and power off, it is necessary
to supply the resistor to prevent condensation.
Immediately put the cover back in place after installation while ensuring
its seal is clean. Never leave actuator electrical components without
their protection cover.
In case of water intrusion:
dry electrical components before putting back the cover.
check electrical insulation.
4.6
Wiring the external ground terminal
How to wire the external ground terminal
1. Crimp the end of the earth cable with
a 6mm ring lug.
2. Fix it on the housing using a 5mm Allen
key, at its location next to the cable
entries.