INSTALLATION OF THE "MODULE 600" UNIT
- Choose where to install the machine
according to the layout of the room, the
number of units to be installed and any
limitations imposed by the architecture.
Check that installation and maintenance
of the machine is possible in the position
chosen.
- Install four M8 threaded rods into the
ceiling to hold the frame.
Proceed as follows to install the FCL unit:
- Overturn the FCL cassette fan coil box.
- Open the cardboard package.
- Remove the box, it is recommended to
make incisions on the corners of the box
and to remove the cardboard one piece
at a time.
- Remove the upper part of the packaging
shell used to protect the unit during
transport.
- If necessary, mount any accessories
(electric resistances, fresh air kit or flow
to adjacent room, hot water valve). Carry
out these operations before installing the
unit on the ceiling.
AT TENTION: consult the accessory
manuals.
- Do not handle the unit using the hydraulic
connections but use the appropriate
brackets.
- Lift the unit carefully using the brackets
and holding it slightly inclined. Fix it to
the 4 threaded rods using the 8 nuts of
which 4 are self-locking. Act on the nuts
to adjust the height, finally check that the
unit is installed in a horizontal position.
- Feed the hydraulic lines through the
suspended-ceiling to the attachment
plate on the unit;
- Make the hydraulic connections as
described in the relative chapter.
- Take the condensate drain pipe to the
respective fitting on the attachment
plate;
- Bleed the system, the vent valve for
the two-pipe circuit is external on the
connections plate. The vent valve
for the heating circuit of the 4-pipe
system is internal, to access remove the
polystyrene basin.
- Connect the condensate drain as
described in the relative chapter.
- Take the electric power supply cables and
control cables in proximity of the electric
box; make sure that the cables are long
enough to follow the movement of the
electric box on the guides during the
assembly and disassembly phases.
- The electric box is supplied with grid
accessories (GLL10/ GLF10, GLL10R/
GLF10EH e GLL10 M/ GLF10 M).
- Consult the grid accessories manuals. The
instructions for mounting and connection
of the electric box are contained in the
manual supplied with the grid accessory.
- After having completed the connections
and the electric box is inserted in its
housing in the FCL unit, fix it using the
two screws.
ATTENTION: fix the safety cable to the
electric box screw fastener positioned
at the side of the hydraulic connections.
The safety cable snap hook must then be
attached to the grid frame.
- For GLL10M/GLF10M e GLL10R/GLF10EH
only: apply any air probe (SA) to the
centre of the fan grid, fix the cable using
the supplied straps, lay the excess cable
in the grooves made in the polystyrene.
- The grill frame must be positioned
in a way that the AERMEC logo holder
corresponds with the corner of the
electric box.
- Mount the grill to the safety cable.
- For GLL10M/GLF10M e GLL10R/GLF10EH
only: make the connections between the
electric box and the receiver.
- Fix the grid using the 4 screws.
ATTENTION!! tighten the screws with
maximum coupling torque of 0.45 Nm.
It is advised to use a screwdriver, do not
use non-calibrated electric screwdrivers.
An excessive coupling torque will damage
the tray irreparably.
- Adjust the position of the unit by the
support bracket by means of the nuts, in
a way that the unit is level and the frame
rests slightly in the suspended ceiling.
- Start the fan coil and carry out a
functioning test. The functions are
described in the user manual.