4. Installation
pict. 1
pict. 2
Setting up
-
Check the package for visible damages
- When unpacking handle all parts of consignment with care.
- Remove carefully the upper part of the inside package (withdraw
slowly (pict.. 1).
Please look that parts of the milling machine do not become
wedged with the package.
- Remove cartons containing accessories (pict.2)
Please look for the milling arm being fixed.
old the milling machine at the column
- H
Do not hold at the milling arm !
- Withdraw the machine a little bit and then hold
it at the basic plate to take the milling machine out.
- Check all parts for visible damages. Place all parts of inner
package back into the outer carton.
Store the complete package for an eventual return to manufacturer.
If you should intend to destruct the package, please be so kind
to return the complete package to SCHICK.
The S2-Master is equipped with adjustable stands. When using a level
for telescopic crowns, the S2-Master has to be calibrated exactly with
a spirit level by screwing the stands clockwise or anti-clockwise.
Connect the milling machine with the mains supply by placing
the mains cable at first into the socket situated on the back
side of the milling machine and then into a safe wall socket
with earth connection.
Please check that all plug connections are readily fixed !
6
Installation and setting up