7.2. Commissioning, volume level and operating
temperature
Note: If a different fill level is required than the
self-established minimum level after start (op-
erational ready and installed top-up), the vessel
should be filled to reflect the minimum required
level needed for the actual system temperature,
after completing the commissioning procedure
on the control unit. For better understanding,
study the diagrams below and the paragraph on
maintenance, vessel draining and re-filling later in
this document.
Example 1
Max. design temp.:
Max. fill level:
Water feed, top-up:
Min. design temp.:
Example 3
Max. design temp.:
Max. fill level:
Water feed, top-up:
Min. design temp.:
Installation and operating instructions Wilo-Sinum
50 °C
92 %
12 %
10 °C
Actual temperature [°C]
25 °C
92 %
12 %
6 °C
Actual temperature [°C]
Example 2
Max. design temp.:
80 °C
Max. fill level:
92 %
Water feed, top-up:
12 %
Min. design temp.:
10 °C
Example 4
Max. design temp.:
40 °C
Max. fill level:
92 %
Water feed, top-up:
12 %
Min. design temp.:
6 °C
Fig. FM.037.V01.15
English
21